  • EnergyAustralia continues to provide good supply into the system.
  • At Yallourn, Units 2, 3 and 4 are online and running. Unit 1 is offline for maintenance.  
  • Both units at Mt Piper are online and running.
  • EnergyAustralia’s gas asset at Tallawarra will be online for the evening peak. Jeeralang and Newport may operate over the evening peak.  Hallett ran this morning and will come offline before running again for the evening peak. 