News

EnergyAustralia continues to provide good supply to the National Electricity Market.

  • At Yallourn, all units are online and running.  
  • At Mt Piper, Units 1 and 2 are running.  
  • EnergyAustralia’s gas assets at Newport and Jeeralang are available for market requirements today. Tallawarra A may run this afternoon.  Hallett ran last night and this morning. 
  • Tallawarra B, EnergyAustralia’s new gas peaking power station, is online for synchronisation testing, ahead of hold point testing. Commercial operation expected in late February.

Due to tomorrow’s public holiday the next update will be on Monday, 28 January.