News

March 5, 2024

EnergyAustralia is continuing to provide good supply to the National Electricity Market.

  •  At Yallourn, Units 1, 2 and 3 are online and running. Unit 4 is offline for repairs.
  •  At Mt Piper, both units are running.  
  •  EnergyAustralia’s gas assets at Hallett ran last night for the evening peak. Tallawarra A, Newport, Jeeralang and Hallett are available for market requirements today.
  •  Tallawarra B, EnergyAustralia’s new gas-peaking power station, is continuing pre-commissioning works.