News

February 5, 2024

EnergyAustralia has continued to provide good supply to the National Electricity Market through the period of hot weather over the weekend.

  • At Yallourn, units 2, 3 and 4 are online and running. Unit 1 is offline for repairs.
  • At Mt Piper, both units are running.  
  • EnergyAustralia’s Tallawarra A gas asset is online. Hallett, Newport and Jeeralang are available for market requirements. Tallawarra B, EnergyAustralia’s new gas-peaking power station, is continuing pre-commissioning testing works.