News

June 5, 2024
  • At Yallourn, Units 2, 3 and 4 are online and running, with Unit 1 remaining offline due to a major outage. 
  • At Mt Piper, Units 1 and 2 are online and available.
  • Newport is currently offline due to maintenance, however is expected to be available from later tonight.
  • Tallawarra A, Jeeralang and Hallett are online and available.
  • Tallawarra B, EnergyAustralia’s new gas-peaking power station, is awaiting release.