- At Yallourn, Units 2, 3 and 4 are online and running, with Unit 1 remaining offline due to a major outage.
- At Mt Piper, Units 1 and 2 are online and available.
- Our gas assets at Newport, Jeeralang, Hallett and Tallawarra A are available.
- Tallawarra A and Hallett both ran yesterday and this morning. Jeeralang ran last night.
- Tallawarra B, EnergyAustralia’s new gas-peaking power station, is awaiting release.