We continue to provide good supply into the National Electricity Market.

  • At Yallourn, units 2, 3 and 4 are online and running. Unit 1 is offline for repairs.
  • At Mt Piper, both units are running.  
  • EnergyAustralia’s Tallawarra A, Hallett, Newport and Jeeralang are available for market requirements. 
  • Tallawarra B, EnergyAustralia’s new gas-peaking power station, is continuing pre-commissioning works.